By Joe Jarosz
Northeast News
January 28, 2015
The first exterior pre-cast wall panels were installed at the Streetcar Vehicle Maintenance Facility, also known as Singleton Yard, located at Third and Holmes Streets, using a 133-foot crane on Monday, Jan. 26. The heaviest precast wall panel weighs 47,360 lbs. Nearly 50 precast exterior panels will be used. This area of Holmes Street will be closed to thru traffic until Friday, Jan. 30, unless otherwise noted. The project is expected to be completed this summer.